Town of Yacolt's FY 2017 Seal Coat Project
2-W-951(004)-1
2-W-951(004)-1
FY 2017 Seal Coat Project
Multiple Locations
FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $97,284
County: Clark | Legislative District: 18 | Project Length: 0.45 | TIB Engineer: Chris Langhoff | Last Payment Date: 03/15/2017
Project Information
Lead Agency | YACOLT |
Funding Year | 2017 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 18 |
Congressional District | 3 |
Federal Route Number | A068 |
Project Length | 0.45 mi. |
ADT | 250 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Pete Roberts |
Contact Email | pete.roberts@townofyacolt.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 03/15/2017 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2015 | |
Delayed Project Date | 07/01/2018 | |
Predesign Approval | ||
Design Approval | 01/15/2016 | 12/28/2015 |
Bid Auth. Approval | 04/01/2016 | 06/20/2016 |
Construction Approval | 06/30/2016 | 07/26/2016 |
Project Closeout | 10/31/2016 | 03/08/2017 |
Audit Date | 03/15/2017 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 12,345 | 12,500 |
Right of Way | 0 | 0 |
Total Design | 12,345 | 12,500 |
Construction Engineering | 12,343 | 16,905 |
Construction Contract | 82,297 | 47,785 |
Other Construction | 37,619 | 20,094 |
Total Construction | 132,259 | 84,784 |
Funding Surplus | - 47,320 | |
Total TIB Funding | 97,284 | 97,284 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
YACOLT | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Contractor will complete prep work (digouts, crack sealing, etc). County will complete the chipseal and striping.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |