City of Ridgefield's FY 2014 Overlay Project

2-W-950(002)-1

2-W-950(002)-1
FY 2014 Overlay Project

Multiple Locations

FY 2014 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $158,903

County: Clark   |   Legislative District: 18   |   Project Length: 0.27   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 03/16/2015

Project Information

Lead Agency RIDGEFIELD
Funding Year 2014
Program SCPP
Current Phase Audit
Legislative District 18
Congressional District 3
Federal Route Number 9999
Project Length 0.27 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Bryan Kast
Contact Email bryan.kast@ci.ridgefield.wa.us
TIB Engineer Chris Langhoff
Last Payment Date 03/16/2015

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2012
Delayed Project Date 07/01/2015  
Predesign Approval
Design Approval 01/01/2013 04/29/2013
Bid Auth. Approval 06/01/2014 03/25/2014
Construction Approval 04/25/2014 04/24/2014
Project Closeout 04/01/2015 03/05/2015
Audit Date   03/16/2015
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 13,500 0
Right of Way 0 0
Total Design 13,500 0
     
Construction Engineering 9,720 0
Construction Contract 121,905 176,559
Other Construction 0 0
Total Construction 131,625 176,559
     
Funding Increase 21,645  
Funding Surplus - 7,867  
Total TIB Funding 158,903 176,559

Local Funding Partners

Funding Amount Percent
RIDGEFIELD 17,656 10.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 17,656 10.0%

Project Description

This project will repair failed areas of pavement and place a 2 inch overlay on S. 56th Place from S. 1st Circle to S. 6th Way. There are 2 sidewalk ramps that will be reconstructed to meet current standards.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.