Projects — TIB Project Information
TIB Project Information
City of La Center's 2021 Overlay
2-W-949(004)-1
2-W-949(004)-1
2021 Overlay
One Location
FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $134,728
County: Clark | Legislative District: 18 | Project Length: 0.45 | TIB Engineer: Chris Langhoff | Last Payment Date: 10/17/2022
Project Information
Lead Agency | LA CENTER |
Funding Year | 2023 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 18 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.45 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Tony Cooper |
Contact Email | acooper@ci.lacenter.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 10/17/2022 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
Predesign Approval | ||
Design Approval | 02/01/2022 | 12/06/2021 |
Bid Auth. Approval | 06/01/2022 | 05/09/2022 |
Construction Approval | 06/30/2022 | 06/10/2022 |
Project Closeout | 09/30/2022 | 10/05/2022 |
Audit Date | 10/17/2022 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 1,454 |
Construction Contract | 169,854 | 215,171 |
Other Construction | 0 | 0 |
Total Construction | 169,854 | 216,625 |
Funding Surplus | - 35,126 | |
Total TIB Funding | 134,728 | 216,625 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LA CENTER | 81,897 | 37.8% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 81,897 | 37.8% |
Project Description
2150 LF of 12-wide travel lane will be paved at a 2 inch depth. 200 LF of subgrade is failing and 2 inch of base and geogrid will be replaced. Reconstruct 200 lineal feet of pavement and base and stabilize subgrade with base and geogrid and paved.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |