City of La Center's FY 2013 Overlay Project
2-W-949(002)-1
2-W-949(002)-1
FY 2013 Overlay Project
Multiple Locations
FY 2013 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $125,413
County: Clark | Legislative District: 18 | Project Length: 2.34 | TIB Engineer: Chris Langhoff | Last Payment Date: 10/01/2014
Project Information
Lead Agency | LA CENTER |
Funding Year | 2013 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 18 |
Congressional District | 3 |
Federal Route Number | D061 |
Project Length | 2.34 mi. |
ADT | 300 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Jeff Sarvis |
Contact Email | jsarvis@ci.lacenter.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 10/01/2014 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2011 | |
Delayed Project Date | 07/01/2014 | |
Predesign Approval | ||
Design Approval | 01/01/2012 | 12/13/2011 |
Bid Auth. Approval | 05/01/2012 | 12/13/2011 |
Construction Approval | 04/01/2013 | 12/03/2012 |
Project Closeout | 08/01/2014 | 09/22/2014 |
Audit Date | 10/01/2014 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 99,687 |
Right of Way | 0 | 1,803 |
Total Design | 0 | 101,490 |
Construction Engineering | 0 | 9,501 |
Construction Contract | 125,000 | 576,580 |
Other Construction | 0 | 0 |
Total Construction | 125,000 | 586,081 |
Funding Increase | 14,142 | |
Funding Surplus | - 13,729 | |
Total TIB Funding | 125,413 | 687,571 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LA CENTER | 148,085 | 21.5% |
WSDOT Funding | 0 | 0.0% |
STP | 414,073 | 67.9% |
Total Local Funding | 562,158 | 81.8% |
Project Description
The project consists of rubbilizing the existing surface and placing a 5 inch asphalt overlay on top.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |