The pavement condition rating of the segments are as follows Lawson Street - Front St to Mitchell St 52 Mitchell Street - Lawson St to Gough St 50
Projects — TIB Project Information
TIB Project Information
City of Sumas's FY 2022 Overlay Project
2-W-841(005)-1
2-W-841(005)-1
FY 2022 Overlay Project
Multiple Locations
FY 2022 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $147,266
County: Whatcom | Legislative District: 42 | Project Length: 0.21 | TIB Engineer: Chris Langhoff | Last Payment Date: 08/15/2022
Project Information
Lead Agency | SUMAS |
Funding Year | 2022 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 42 |
Congressional District | 1 |
Federal Route Number | 9999 |
Project Length | 0.21 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Sunny Aulakh |
Contact Email | saulakh@cityofsumas.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 08/15/2022 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2020 | |
Delayed Project Date | 07/01/2023 | |
Predesign Approval | ||
Design Approval | 02/01/2021 | 12/10/2020 |
Bid Auth. Approval | 05/01/2022 | 05/26/2022 |
Construction Approval | 07/15/2022 | 07/07/2022 |
Project Closeout | 12/31/2022 | 08/12/2022 |
Audit Date | 08/15/2022 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 12,197 | 12,591 |
Right of Way | 0 | 0 |
Total Design | 12,197 | 12,591 |
Construction Engineering | 12,197 | 14,517 |
Construction Contract | 128,064 | 136,521 |
Other Construction | 0 | 0 |
Total Construction | 140,261 | 151,038 |
Funding Increase | 17,954 | |
Funding Surplus | - 23,146 | |
Total TIB Funding | 147,266 | 163,629 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SUMAS | 16,363 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 16,363 | 10.0% |
Project Description
This segment of Lawson and Mitchell Streets abuts an elementary school to be reconstructed beginning Fall 2020. The school will upgrade all ADA to compliance.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |