Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Everson's Maintenance Crack Seal

2-W-838(003)-1

2-W-838(003)-1
Maintenance Crack Seal

FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $24,116

County: Whatcom   |   Legislative District: 42   |   Project Length: 4.17   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 12/01/2022

Project Information

Lead Agency EVERSON
Funding Year 2023
Program SCPP
Current Phase Audit
Legislative District 42
Congressional District 1
Federal Route Number 9999
Project Length 4.17 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Dave Schoonover
Contact Email dschoonover@thecityofeverson.com
TIB Engineer Chris Langhoff
Last Payment Date 12/01/2022

Project Schedule

  Target Date Actual Date
Project Selection Date   08/18/2022
Delayed Project Date 07/01/2025  
Predesign Approval
Design Approval 09/01/2022 08/25/2022
Bid Auth. Approval 09/01/2022 08/25/2022
Construction Approval 09/01/2022 08/25/2022
Project Closeout 11/30/2022 11/17/2022
Audit Date   12/01/2022
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 22,207 25,386
Other Construction 0 0
Total Construction 22,207 25,386
     
Funding Increase 1,909  
Total TIB Funding 24,116 25,386

Local Funding Partners

Funding Amount Percent
EVERSON 1,270 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 1,270 5.0%

Project Description

Maintenance crack seal

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments