City of Everson's 2017 Emergency Pavement Repair Project

2-W-838(002)-1

2-W-838(002)-1
2017 Emergency Pavement Repair Project

Various Location

FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $44,945

County: Whatcom   |   Legislative District: 42   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 08/30/2017

Project Information

Lead Agency EVERSON
Funding Year 2018
Program SCPP
Current Phase Audit
Legislative District 42
Congressional District 1
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Dave Schoonover
Contact Email dschoonover@ci.everson.wa.us
TIB Engineer Chris Langhoff
Last Payment Date 08/30/2017

Project Schedule

  Target Date Actual Date
Project Selection Date   05/09/2017
Delayed Project Date 07/01/2019  
Predesign Approval
Design Approval 06/01/2017 05/22/2017
Bid Auth. Approval 06/01/2017 05/22/2017
Construction Approval 06/01/2017 05/22/2017
Project Closeout 08/31/2017 08/29/2017
Audit Date   08/30/2017
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 44,945 47,310
Other Construction 0 0
Total Construction 44,945 47,310
     
Total TIB Funding 44,945 47,310

Local Funding Partners

Funding Amount Percent
EVERSON 2,365 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 2,365 5.0%

Project Description

See approved repair list.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.