The pavement condition rating of the segment are as follow Prevdell Road - W Main St to SR 20 54 Pipeline Road - E Main St to SR 20 54
Projects — TIB Project Information
TIB Project Information
Town of Lyman's 2021 Overlay
2-W-835(005)-1
2-W-835(005)-1
2021 Overlay
Multiple Locations
FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $160,719
County: Skagit | Legislative District: 39 | Project Length: 0.33 | TIB Engineer: Chris Langhoff | Last Payment Date: 07/03/2023
Project Information
Lead Agency | LYMAN |
Funding Year | 2023 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 39 |
Congressional District | 1 |
Federal Route Number | 9999 |
Project Length | 0.33 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Eddie Hills |
Contact Email | mayor@townoflyman.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 07/03/2023 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
Predesign Approval | ||
Design Approval | 03/01/2022 | 03/16/2022 |
Bid Auth. Approval | 05/01/2022 | 04/06/2022 |
Construction Approval | 05/15/2022 | 07/08/2022 |
Project Closeout | 04/30/2023 | 06/21/2023 |
Audit Date | 07/03/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 20,000 | 25,786 |
Right of Way | 0 | 0 |
Total Design | 20,000 | 25,786 |
Construction Engineering | 20,000 | 826 |
Construction Contract | 167,637 | 134,106 |
Other Construction | 0 | 0 |
Total Construction | 187,637 | 134,933 |
Funding Surplus | - 46,918 | |
Total TIB Funding | 160,719 | 160,719 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LYMAN | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Work for this segment will include grind, HMA pavement repair, 2 inch HMA overlay, and other work as necessary for the needed improvements.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |