Projects — TIB Project Information
TIB Project Information
Town of Lyman's FY 2019 Seal Coat Project
2-W-835(004)-1
2-W-835(004)-1
FY 2019 Seal Coat Project
Multiple Locations
FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $69,647
County: Skagit | Legislative District: 39 | Project Length: 0.88 | TIB Engineer: Chris Langhoff | Last Payment Date: 01/02/2020
Project Information
Lead Agency | LYMAN |
Funding Year | 2019 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 39 |
Congressional District | 1 |
Federal Route Number | 9999 |
Project Length | 0.88 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Eddie Hills |
Contact Email | mayor@townoflyman.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 01/02/2020 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/17/2017 | |
Delayed Project Date | 07/01/2020 | |
Predesign Approval | ||
Design Approval | 01/01/2018 | 02/01/2018 |
Bid Auth. Approval | 04/01/2018 | 02/01/2018 |
Construction Approval | 05/01/2018 | 02/01/2018 |
Project Closeout | 12/31/2019 | 12/20/2019 |
Audit Date | 01/02/2020 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 6,528 |
Right of Way | 0 | 0 |
Total Design | 0 | 6,528 |
Construction Engineering | 0 | 0 |
Construction Contract | 102,225 | 54,486 |
Other Construction | 0 | 8,633 |
Total Construction | 102,225 | 63,119 |
Funding Surplus | - 32,578 | |
Total TIB Funding | 69,647 | 69,647 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LYMAN | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project will chip seal Main Street from the east to west town limits
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |