Town of Lyman's FY 2018 Overlay Project
2-W-835(002)-1
2-W-835(002)-1
FY 2018 Overlay Project
Multiple Locations
FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $118,084
County: Skagit | Legislative District: 39 | Project Length: 0.09 | TIB Engineer: Chris Langhoff | Last Payment Date: 10/16/2017
Project Information
Lead Agency | LYMAN |
Funding Year | 2018 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 39 |
Congressional District | 1 |
Federal Route Number | 9999 |
Project Length | 0.09 mi. |
ADT | 250 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Eddie Hills |
Contact Email | mayor@townoflyman.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 10/16/2017 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2016 | |
Delayed Project Date | 07/01/2019 | |
Predesign Approval | ||
Design Approval | 01/01/2017 | 12/22/2016 |
Bid Auth. Approval | 03/15/2017 | 03/20/2017 |
Construction Approval | 04/11/2017 | 04/17/2017 |
Project Closeout | 10/31/2017 | 10/13/2017 |
Audit Date | 10/16/2017 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 12,500 | 12,492 |
Right of Way | 0 | 0 |
Total Design | 12,500 | 12,492 |
Construction Engineering | 15,000 | 19,267 |
Construction Contract | 92,100 | 90,834 |
Other Construction | 0 | 0 |
Total Construction | 107,100 | 110,101 |
Funding Increase | 5,872 | |
Funding Surplus | - 7,388 | |
Total TIB Funding | 118,084 | 122,593 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LYMAN | 4,509 | 3.7% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 4,509 | 3.7% |
Project Description
This project repairs areas of pavement failure, grinds, provides a 2-inch overlay and upgrades 4 ramps to current standards on Lyman Avenue bewteen W Main Street and Lyman Elementary School.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |