Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Town of Lyman's FY 2014 Seal Coat Project

2-W-835(001)-1

2-W-835(001)-1
FY 2014 Seal Coat Project

Multiple Locations

FY 2014 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $10,239

County: Skagit   |   Legislative District: 39   |   Project Length: 0.34   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 12/23/2013

Project Information

Lead Agency LYMAN
Funding Year 2014
Program SCPP
Current Phase Audit
Legislative District 39
Congressional District 1
Federal Route Number 9999
Project Length 0.34 mi.
ADT 0
Functional Class Local Access
Type of Work Resurfacing
Project Contact Debra Heinzman
Contact Email clerk_lyman@msn.com
TIB Engineer Chris Langhoff
Last Payment Date 12/23/2013

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2012
Delayed Project Date 07/01/2015  
Predesign Approval
Design Approval 01/01/2013 12/07/2012
Bid Auth. Approval 06/01/2013 12/07/2012
Construction Approval 07/01/2014 08/06/2013
Project Closeout 12/02/2013 12/11/2013
Audit Date   12/23/2013
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 845
Construction Contract 11,499 9,394
Other Construction 0 0
Total Construction 11,499 10,239
     
Funding Increase 282  
Funding Surplus - 1,542  
Total TIB Funding 10,239 10,239

Local Funding Partners

Funding Amount Percent
LYMAN 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

This project will chip seal the following segments First Street - Main St to Meyers Ave Second Street - Main to Meyers Ave Third Street - Main St to Meyers Ave Meyers Ave - First St to Third St

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments