The PCR ratingsfor the selected segments are as follows California Street - Maple St to Hamilton Ave 50 Maple Street - Cumberland St to Nolle Ave 45 Maple Street - Nolle Ave to Railroad Ave 50 Nolle Avenue - Noble Ave to Maple Str 45 Pettit Street - Lyman- Hamilton Rd to Maple St 52 Pettit Street - Maple St to Hamilton Ave 50 Pettit Street - S Stream Crossing to Cascade Trail Crossing 50
Projects — TIB Project Information
TIB Project Information
Town of Hamilton's FY 2014 Red Town Project
2-W-833(002)-1
2-W-833(002)-1
FY 2014 Red Town Project
Multiple Locations
FY 2014 Small City Preservation Program
Current Phase : Withdrawn
Total TIB Funding : $0
County: Skagit | Legislative District: 39 | Project Length: 0.68 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | HAMILTON |
Funding Year | 2014 |
Program | SCPP |
Current Phase | Withdrawn |
Legislative District | 39 |
Congressional District | 1 |
Federal Route Number | 9999 |
Project Length | 0.68 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Joan Cromley |
Contact Email | townofhamilton.2010@gmail.com |
TIB Engineer | Chris Langhoff |
Last Payment Date |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2012 | |
Delayed Project Date | 07/01/2015 | |
Predesign Approval | ||
Design Approval | 02/28/2013 | |
Bid Auth. Approval | 06/01/2013 | |
Construction Approval | 07/01/2013 | |
Project Closeout | 10/31/2013 | |
Audit Date | ||
Withdrawn Date | 02/22/2013 |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 0 | 0 |
Other Construction | 0 | 0 |
Total Construction | 0 | 0 |
Total TIB Funding | 0 | 0 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
HAMILTON | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project will prelevel and provide a 2 inch overlay of the following Streets Pettit Street, Maple Street, Railroad Avenue, Nolle Avenue and California Street. In addition small areas of base failure will be dug out and repaired.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |