The PCR ratings for the selected segments are as follows Pettit Street - SR-20 to stream crossing 52 Lyman-Hamilton Way - Pettit St to Cumberland St 52 Cumberland Street - Lyman-Hamilton Hwy to Noble Ave 44 California Street - Maple St to Hamilton Ave 50 Maple Street - Cumberland St to Nolle Ave 45 Maple Street - Nolle Ave to Railroad Ave 50 Nolle Avenue - Noble Ave to Maple St 45 Pettit Street - Lyman- Hamilton Rd to Maple St 52 Pettit Street - Maple St to Hamilton Ave 50 Pettit Street - S Stream Crossing to Cascade Trail Crossing 50
Projects — TIB Project Information
TIB Project Information
Town of Hamilton's FY 2013 Overlay Project
2-W-833(001)-1
2-W-833(001)-1
FY 2013 Overlay Project
Multiple Locations
FY 2013 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $319,897
County: Skagit | Legislative District: 39 | Project Length: 1.15 | TIB Engineer: Chris Langhoff | Last Payment Date: 09/16/2013
Project Information
Lead Agency | HAMILTON |
Funding Year | 2013 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 39 |
Congressional District | 1 |
Federal Route Number | 9999 |
Project Length | 1.15 mi. |
ADT | 150 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Joan Cromley |
Contact Email | Townofhamilton.2010@gmail.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 09/16/2013 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2011 | |
Delayed Project Date | 07/01/2014 | |
Predesign Approval | ||
Design Approval | 01/01/2012 | 12/01/2011 |
Bid Auth. Approval | 05/01/2012 | 06/06/2013 |
Construction Approval | 07/01/2013 | 06/27/2013 |
Project Closeout | 09/01/2013 | 08/29/2013 |
Audit Date | 09/16/2013 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 18,772 | 21,867 |
Right of Way | 0 | 0 |
Total Design | 18,772 | 21,867 |
Construction Engineering | 23,772 | 18,923 |
Construction Contract | 267,106 | 279,107 |
Other Construction | 0 | 0 |
Total Construction | 290,878 | 298,030 |
Funding Increase | 15,580 | |
Funding Surplus | - 5,333 | |
Total TIB Funding | 319,897 | 319,897 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
HAMILTON | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project will grind and overlay 0.47 miles of streets in Hamilton with digouts in area of base failure. The segments include the following Pettit Street - SR-20 to stream crossing Lyman-Hamilton Way - Pettit St to Cumberland St Cumberland Street - Lyman-Hamilton Hwy to Noble Ave California Street - Maple St to Hamilton Ave Maple Street - Cumberland St to Nolle Ave Maple Street - Nolle Ave to Railroad Ave Nolle Avenue - Noble Ave to Maple St Pettit Street - Lyman- Hamilton Rd to Maple St Pettit Street - Maple St to Hamilton Ave Pettit Street - S Stream Crossing to Cascade Trail Crossing
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |