Town of Concrete's FY 2022 Overlay Project

2-W-832(007)-1

2-W-832(007)-1
FY 2022 Overlay Project

Multiple Locations

FY 2022 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $182,793

County: Skagit   |   Legislative District: 39   |   Project Length: 0.42   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 11/01/2021

Project Information

Lead Agency CONCRETE
Funding Year 2022
Program SCPP
Current Phase Audit
Legislative District 39
Congressional District 1
Federal Route Number 9999
Project Length 0.42 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Anderea Fichter
Contact Email adnreaF@concretewa.gov
TIB Engineer Chris Langhoff
Last Payment Date 11/01/2021

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2020
Delayed Project Date 07/01/2023  
Predesign Approval
Design Approval 02/01/2021 01/07/2021
Bid Auth. Approval 04/07/2021 04/07/2021
Construction Approval 04/28/2021 05/12/2021
Project Closeout 10/31/2021 10/21/2021
Audit Date   11/01/2021
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 7,599 11,955
Right of Way 0 0
Total Design 7,599 11,955
     
Construction Engineering 22,797 18,064
Construction Contract 159,604 171,054
Other Construction 0 0
Total Construction 182,401 189,118
     
Funding Surplus - 7,207  
Total TIB Funding 182,793 201,073

Local Funding Partners

Funding Amount Percent
CONCRETE 18,280 9.1%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 18,280 9.1%

Project Description

The project scope will be to provide a 2' HMA overlay to Limestone Street from N. Superior to E Ave. and provide for crosswalk and channeliztiaon improvements.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments