Town of Concrete's FY 2014 Red Town Project

2-W-832(003)-1

2-W-832(003)-1
FY 2014 Red Town Project

Multiple Locations

FY 2014 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $280,312

County: Skagit   |   Legislative District: 39   |   Project Length: 0.85   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 12/23/2013

Project Information

Lead Agency CONCRETE
Funding Year 2014
Program SCPP
Current Phase Audit
Legislative District 39
Congressional District 1
Federal Route Number 9999
Project Length 0.85 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Andrea Fichter
Contact Email andreaf@concretewa.gov
TIB Engineer Chris Langhoff
Last Payment Date 12/23/2013

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2012
Delayed Project Date 07/01/2015  
Predesign Approval
Design Approval 01/01/2013 12/17/2012
Bid Auth. Approval 07/25/2013 07/24/2013
Construction Approval 08/19/2013 08/20/2013
Project Closeout 12/31/2013 12/13/2013
Audit Date   12/23/2013
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 20,000 13,213
Right of Way 0 0
Total Design 20,000 13,213
     
Construction Engineering 20,000 25,271
Construction Contract 210,000 241,008
Other Construction 0 820
Total Construction 230,000 267,099
     
Funding Increase 32,746  
Funding Surplus - 2,434  
Total TIB Funding 280,312 280,312

Local Funding Partners

Funding Amount Percent
CONCRETE 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

This project will grind and provide a 2-inch overlay of E Main Street between the Baker River Bridge and N Everett to and North Dillard Avenue between SR 20 and Main Street. In addition, 4 ADA ramps will be upgraded.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.