The PCR ratings for the selected segments are as follows E Main Street - Bridge End to Everett St 50 N Dillard Avenue - SR 20 to Main St 44 N Everett Avenue - SR 20 to E Main St 50
Projects — TIB Project Information
TIB Project Information
Town of Concrete's FY 2014 Red Town Project
2-W-832(003)-1
2-W-832(003)-1
FY 2014 Red Town Project
Multiple Locations
FY 2014 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $280,312
County: Skagit | Legislative District: 39 | Project Length: 0.85 | TIB Engineer: Chris Langhoff | Last Payment Date: 12/23/2013
Project Information
Lead Agency | CONCRETE |
Funding Year | 2014 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 39 |
Congressional District | 1 |
Federal Route Number | 9999 |
Project Length | 0.85 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Andrea Fichter |
Contact Email | andreaf@concretewa.gov |
TIB Engineer | Chris Langhoff |
Last Payment Date | 12/23/2013 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2012 | |
Delayed Project Date | 07/01/2015 | |
Predesign Approval | ||
Design Approval | 01/01/2013 | 12/17/2012 |
Bid Auth. Approval | 07/25/2013 | 07/24/2013 |
Construction Approval | 08/19/2013 | 08/20/2013 |
Project Closeout | 12/31/2013 | 12/13/2013 |
Audit Date | 12/23/2013 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 20,000 | 13,213 |
Right of Way | 0 | 0 |
Total Design | 20,000 | 13,213 |
Construction Engineering | 20,000 | 25,271 |
Construction Contract | 210,000 | 241,008 |
Other Construction | 0 | 820 |
Total Construction | 230,000 | 267,099 |
Funding Increase | 32,746 | |
Funding Surplus | - 2,434 | |
Total TIB Funding | 280,312 | 280,312 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CONCRETE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project will grind and provide a 2-inch overlay of E Main Street between the Baker River Bridge and N Everett to and North Dillard Avenue between SR 20 and Main Street. In addition, 4 ADA ramps will be upgraded.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |