Projects — TIB Project Information
TIB Project Information
Town of Coupeville's 2022 Seal Coat Award
2-W-827(014)-1
2-W-827(014)-1
2022 Seal Coat Award
Multiple Locations
FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $77,390
County: Island | Legislative District: 10 | Project Length: 0.71 | TIB Engineer: Chris Langhoff | Last Payment Date: 04/15/2024
Project Information
Lead Agency | COUPEVILLE |
Funding Year | 2024 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 10 |
Congressional District | 2 |
Federal Route Number | 9999 |
Project Length | 0.71 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Kelly Riepma |
Contact Email | publicworks@townofcoupeville.org |
TIB Engineer | Chris Langhoff |
Last Payment Date | 04/15/2024 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
Predesign Approval | ||
Design Approval | 02/01/2023 | 02/06/2023 |
Bid Auth. Approval | 06/15/2023 | 02/06/2023 |
Construction Approval | 06/30/2023 | 12/07/2023 |
Project Closeout | 02/29/2024 | 04/01/2024 |
Audit Date | 04/15/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 10,751 | 0 |
Right of Way | 0 | 0 |
Total Design | 10,751 | 0 |
Construction Engineering | 10,751 | 0 |
Construction Contract | 120,096 | 81,463 |
Other Construction | 0 | 0 |
Total Construction | 130,847 | 81,463 |
Funding Surplus | - 64,208 | |
Total TIB Funding | 77,390 | 81,463 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
COUPEVILLE | 4,073 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 4,073 | 5.0% |
Project Description
Chip seal of following segments NE 3rd Street - N Main St to NE Albion St NE 4th Street - N Main St to NE Faris St
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |