Town of Coupeville's City-wide Crack Seal

2-W-827(012)-1

2-W-827(012)-1
City-wide Crack Seal

FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $22,800

County: Island   |   Legislative District: 10   |   Project Length: 3.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 12/01/2022

Project Information

Lead Agency COUPEVILLE
Funding Year 2023
Program SCPP
Current Phase Audit
Legislative District 10, 2
Congressional District 2
Federal Route Number 9999
Project Length 3.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Kelly Riepma
Contact Email publicworks@townofcoupeville.org
TIB Engineer Chris Langhoff
Last Payment Date 12/01/2022

Project Schedule

  Target Date Actual Date
Project Selection Date   07/20/2022
Delayed Project Date 07/01/2025  
Predesign Approval
Design Approval 08/01/2022 07/20/2022
Bid Auth. Approval 08/01/2022 07/20/2022
Construction Approval 08/01/2022 07/20/2022
Project Closeout 11/30/2022 11/18/2022
Audit Date   12/01/2022
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 22,800 24,000
Other Construction 0 0
Total Construction 22,800 24,000
     
Total TIB Funding 22,800 24,000

Local Funding Partners

Funding Amount Percent
COUPEVILLE 1,200 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 1,200 5.0%

Project Description

City-wide Crack Seal

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments