S Main Street - SR 20 to S C/L PCR 59
Projects — TIB Project Information
TIB Project Information
Town of Coupeville's FY 2020 Overlay Project
2-W-827(008)-1
2-W-827(008)-1
FY 2020 Overlay Project
Multiple Locations
FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $361,506
County: Island | Legislative District: 10 | Project Length: 0.59 | TIB Engineer: Chris Langhoff | Last Payment Date: 03/01/2022
Project Information
Lead Agency | COUPEVILLE |
Funding Year | 2020 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 10 |
Congressional District | 2 |
Federal Route Number | L151 |
Project Length | 0.59 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Kelly Riepma |
Contact Email | publicworks@townofcoupeville.org |
TIB Engineer | Chris Langhoff |
Last Payment Date | 03/01/2022 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2018 | |
Delayed Project Date | 07/01/2021 | |
Predesign Approval | ||
Design Approval | 01/01/2019 | 01/08/2019 |
Bid Auth. Approval | 04/01/2020 | 03/17/2020 |
Construction Approval | 05/01/2020 | 04/16/2020 |
Project Closeout | 09/30/2021 | 02/28/2022 |
Audit Date | 03/01/2022 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 42,750 | 0 |
Right of Way | 0 | 0 |
Total Design | 42,750 | 0 |
Construction Engineering | 42,750 | 4,209 |
Construction Contract | 537,444 | 286,657 |
Other Construction | 0 | 89,667 |
Total Construction | 580,194 | 380,533 |
Funding Surplus | - 261,438 | |
Total TIB Funding | 361,506 | 380,533 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
COUPEVILLE | 19,027 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 19,027 | 5.0% |
Project Description
Apply 2' overlay, install 19 ADA ramps and miscellaneous drainage repair.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |