Town of Coupeville's FY 2019 Rehabilitation Project
2-W-827(007)-1
2-W-827(007)-1
FY 2019 Rehabilitation Project
Multiple Locations
FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $85,671
County: Island | Legislative District: 10 | Project Length: 0.13 | TIB Engineer: Chris Langhoff | Last Payment Date: 01/30/2019
Project Information
Lead Agency | COUPEVILLE |
Funding Year | 2019 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 10 |
Congressional District | 2 |
Federal Route Number | 9999 |
Project Length | 0.13 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Kimberly Hinds |
Contact Email | engineer@townofcoupeville.org |
TIB Engineer | Chris Langhoff |
Last Payment Date | 01/30/2019 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/17/2017 | |
Delayed Project Date | 07/01/2020 | |
Predesign Approval | ||
Design Approval | 01/01/2018 | 01/04/2018 |
Bid Auth. Approval | 04/01/2018 | 01/04/2018 |
Construction Approval | 05/01/2018 | 01/04/2018 |
Project Closeout | 12/31/2018 | 01/10/2019 |
Audit Date | 01/30/2019 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 6,982 | 0 |
Right of Way | 0 | 0 |
Total Design | 6,982 | 0 |
Construction Engineering | 6,982 | 0 |
Construction Contract | 76,797 | 90,182 |
Other Construction | 0 | 0 |
Total Construction | 83,779 | 90,182 |
Funding Surplus | - 5,090 | |
Total TIB Funding | 85,671 | 90,182 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
COUPEVILLE | 4,511 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 4,511 | 5.0% |
Project Description
This project rehabilates NW 6th Street and Bainbridge Lane using full depth reclamation.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |