Town of Coupeville's FY 2019 Overlay Project

2-W-827(006)-1

2-W-827(006)-1
FY 2019 Overlay Project

Multiple Locations

FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $65,688

County: Island   |   Legislative District: 10   |   Project Length: 0.32   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 01/30/2019

Project Information

Lead Agency COUPEVILLE
Funding Year 2019
Program SCPP
Current Phase Audit
Legislative District 10
Congressional District 2
Federal Route Number 9999
Project Length 0.32 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Kimberly Hinds
Contact Email engineer@townofcoupeville.org
TIB Engineer Chris Langhoff
Last Payment Date 01/30/2019

Project Schedule

  Target Date Actual Date
Project Selection Date   11/17/2017
Delayed Project Date 07/01/2020  
Predesign Approval
Design Approval 01/01/2018 01/04/2018
Bid Auth. Approval 04/01/2018 01/04/2018
Construction Approval 05/01/2018 01/04/2018
Project Closeout 12/31/2018 01/10/2019
Audit Date   01/30/2019
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 5,254 0
Right of Way 0 0
Total Design 5,254 0
     
Construction Engineering 5,254 0
Construction Contract 57,798 69,284
Other Construction 0 0
Total Construction 63,052 69,284
     
Funding Surplus - 2,618  
Total TIB Funding 65,688 69,284

Local Funding Partners

Funding Amount Percent
COUPEVILLE 3,596 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 3,596 5.0%

Project Description

this project provides a 1-inch overlay of the following segments Otis Street - NE 6th St to NE 9th St LaSalle/8th Street - NE 9th St to Leach St Lindsey St - NE 7th to End

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.