TIB Project Information

City of Sultan's FY 2014 Overlay Project

2-P-824(002)-1

2-P-824(002)-1
FY 2014 Overlay Project

Multiple Locations

FY 2014 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $337,451

County: Snohomish   |   Legislative District: 39   |   Project Length: 0.29   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 05/13/2015

Project Information

Lead Agency SULTAN
Funding Year 2014
Program SCPP
Current Phase Audit
Legislative District 39
Congressional District 2
Federal Route Number 9999
Project Length 0.29 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Mick Matheson
Contact Email Mick.matheson@ci.sultan.wa.us
TIB Engineer Greg Armstrong
Last Payment Date 05/13/2015

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2012
Delayed Project Date 07/01/2015  
Predesign Approval
Design Approval 01/01/2013 01/16/2013
Bid Auth. Approval 05/19/2014 05/19/2014
Construction Approval 06/17/2014 06/17/2014
Project Closeout 05/07/2015 05/05/2015
Audit Date   05/13/2015
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 38,903 47,014
Right of Way 0 0
Total Design 38,903 47,014
     
Construction Engineering 38,903 28,634
Construction Contract 259,350 279,565
Other Construction 0 0
Total Construction 298,253 308,199
     
Funding Increase 28,807  
Funding Surplus - 28,512  
Total TIB Funding 337,451 355,213

Local Funding Partners

Funding Amount Percent
SULTAN 17,762 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 17,762 5.0%

Project Description

This project will grind, prelevel and provide a 2-inch overlay of 4th Street between Alder St and Fir St. In addition area of base failure will be repaired and 10 ADA ramps will be upgraded.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments