TIB Project Information

City of Granite Falls's Citywide Crack Seal Program

2-P-820(007)-1

2-P-820(007)-1
Citywide Crack Seal Program

FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $33,323

County: Snohomish   |   Legislative District: 39   |   Project Length: 0.10   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 08/31/2022

Project Information

Lead Agency GRANITE FALLS
Funding Year 2023
Program SCPP
Current Phase Audit
Legislative District 39
Congressional District 2
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Brent Kirk
Contact Email brent.kirk@ci.granite-falls.wa.us
TIB Engineer Greg Armstrong
Last Payment Date 08/31/2022

Project Schedule

  Target Date Actual Date
Project Selection Date   05/02/2022
Delayed Project Date 07/01/2024  
Predesign Approval
Design Approval 05/02/2022 05/02/2022
Bid Auth. Approval 05/02/2022 05/02/2022
Construction Approval 05/02/2022 05/02/2022
Project Closeout 08/31/2022 08/17/2022
Audit Date   08/31/2022
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 35,866 35,076
Other Construction 0 0
Total Construction 35,866 35,076
     
Funding Surplus - 2,543  
Total TIB Funding 33,323 35,076

Local Funding Partners

Funding Amount Percent
GRANITE FALLS 1,753 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 1,753 5.0%

Project Description

Citywide Crack Seal

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.