North Granite Avenue has experienced localized pavement failure (cracking and settling) in various areas.
Projects — TIB Project Information
TIB Project Information
City of Granite Falls's 2021 Small City Maintenance
2-P-820(006)-1
2-P-820(006)-1
2021 Small City Maintenance
Multiple Locations
FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $40,263
County: Snohomish | Legislative District: 39 | Project Length: 0.10 | TIB Engineer: Greg Armstrong | Last Payment Date: 12/01/2022
Project Information
Lead Agency | GRANITE FALLS |
Funding Year | 2023 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 39 |
Congressional District | 2 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Brent Kirk |
Contact Email | brent.kirk@ci.granite-falls.wa.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | 12/01/2022 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2021 | |
Delayed Project Date | 07/01/2024 | |
Predesign Approval | ||
Design Approval | 02/01/2022 | 12/06/2021 |
Bid Auth. Approval | 04/01/2022 | 03/23/2022 |
Construction Approval | 04/13/2022 | 04/18/2022 |
Project Closeout | 11/30/2022 | 11/16/2022 |
Audit Date | 12/01/2022 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 47,500 | 42,383 |
Other Construction | 0 | 0 |
Total Construction | 47,500 | 42,383 |
Funding Surplus | - 7,237 | |
Total TIB Funding | 40,263 | 42,383 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GRANITE FALLS | 2,120 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 2,120 | 5.0% |
Project Description
North Granite Avenue has experienced localized pavement failure (cracking and settling) in various areas. Areas of pavement failure will be removed to a depth not to exceed 12 inches (from finished grade). Crushed gravel and asphalt will be installed and compacted. All surface joints will then be sealed.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |