City of Granite Falls's FY 2020 Overlay Project
2-P-820(004)-1
2-P-820(004)-1
FY 2020 Overlay Project
Multiple Locations
FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $91,090
County: Snohomish | Legislative District: 39 | Project Length: 0.09 | TIB Engineer: Greg Armstrong | Last Payment Date: 02/03/2020
Project Information
Lead Agency | GRANITE FALLS |
Funding Year | 2020 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 39 |
Congressional District | 1 |
Federal Route Number | 9999 |
Project Length | 0.09 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Brent Kirk |
Contact Email | brent.kirk@ci.granite-falls.wa.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | 02/03/2020 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2018 | |
Delayed Project Date | 07/01/2021 | |
Predesign Approval | ||
Design Approval | 01/31/2019 | 01/31/2019 |
Bid Auth. Approval | 03/31/2019 | 03/28/2019 |
Construction Approval | 04/26/2019 | 04/26/2019 |
Project Closeout | 01/31/2020 | 01/21/2020 |
Audit Date | 02/03/2020 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 7,200 | 0 |
Right of Way | 0 | 0 |
Total Design | 7,200 | 0 |
Construction Engineering | 6,300 | 8,452 |
Construction Contract | 81,000 | 92,759 |
Other Construction | 0 | 0 |
Total Construction | 87,300 | 101,211 |
Funding Increase | 12,236 | |
Funding Surplus | - 15,646 | |
Total TIB Funding | 91,090 | 101,211 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GRANITE FALLS | 10,121 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 10,121 | 10.0% |
Project Description
This project grinds and provides a 2-inch overlay on Alder Street between Galena St to Stanley Street
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |