TIB Project Information

City of Granite Falls's FY 2020 Overlay Project

2-P-820(004)-1

2-P-820(004)-1
FY 2020 Overlay Project

Multiple Locations

FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $91,090

County: Snohomish   |   Legislative District: 39   |   Project Length: 0.09   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 02/03/2020

Project Information

Lead Agency GRANITE FALLS
Funding Year 2020
Program SCPP
Current Phase Audit
Legislative District 39
Congressional District 1
Federal Route Number 9999
Project Length 0.09 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Brent Kirk
Contact Email brent.kirk@ci.granite-falls.wa.us
TIB Engineer Greg Armstrong
Last Payment Date 02/03/2020

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2018
Delayed Project Date 07/01/2021  
Predesign Approval
Design Approval 01/31/2019 01/31/2019
Bid Auth. Approval 03/31/2019 03/28/2019
Construction Approval 04/26/2019 04/26/2019
Project Closeout 01/31/2020 01/21/2020
Audit Date   02/03/2020
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 7,200 0
Right of Way 0 0
Total Design 7,200 0
     
Construction Engineering 6,300 8,452
Construction Contract 81,000 92,759
Other Construction 0 0
Total Construction 87,300 101,211
     
Funding Increase 12,236  
Funding Surplus - 15,646  
Total TIB Funding 91,090 101,211

Local Funding Partners

Funding Amount Percent
GRANITE FALLS 10,121 10.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 10,121 10.0%

Project Description

This project grinds and provides a 2-inch overlay on Alder Street between Galena St to Stanley Street

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments