City of Granite Falls's FY 2017 Overlay Project

2-P-820(002)-1

2-P-820(002)-1
FY 2017 Overlay Project

Multiple Locations

FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $150,227

County: Snohomish   |   Legislative District: 39   |   Project Length: 0.45   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 02/01/2017

Project Information

Lead Agency GRANITE FALLS
Funding Year 2017
Program SCPP
Current Phase Audit
Legislative District 39
Congressional District 1
Federal Route Number 2752
Project Length 0.45 mi.
ADT 1,500
Functional Class Minor
Type of Work Resurfacing
Project Contact Brent Kirk
Contact Email brent.kirk@ci.granite-falls.wa.us
TIB Engineer Greg Armstrong
Last Payment Date 02/01/2017

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2015
Delayed Project Date 07/01/2018  
Predesign Approval
Design Approval 01/15/2016 12/07/2015
Bid Auth. Approval 04/15/2016 04/11/2016
Construction Approval 05/16/2016 05/13/2016
Project Closeout 01/31/2017 01/23/2017
Audit Date   02/01/2017
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 26,947 0
Right of Way 0 0
Total Design 26,947 0
     
Construction Engineering 26,947 0
Construction Contract 179,645 158,134
Other Construction 0 0
Total Construction 206,592 158,134
     
Funding Surplus - 83,312  
Total TIB Funding 150,227 158,134

Local Funding Partners

Funding Amount Percent
GRANITE FALLS 7,907 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 7,907 5.0%

Project Description

This project repairs areas of base failure, grinds and provides a 2-inch overlay of Mountain Loop Highway between Quarry Road and North City Limits

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.