City of Granite Falls's FY 2015 Overlay Project
2-P-820(001)-1
2-P-820(001)-1
FY 2015 Overlay Project
Multiple Locations
FY 2015 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $129,378
County: Snohomish | Legislative District: 39 | Project Length: 0.29 | TIB Engineer: Greg Armstrong | Last Payment Date: 02/02/2015
Project Information
Lead Agency | GRANITE FALLS |
Funding Year | 2015 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 39 |
Congressional District | 1 |
Federal Route Number | 2752 |
Project Length | 0.29 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Resurfacing |
Project Contact | Brent Kirk |
Contact Email | brent.kirk@ci.granite-falls.wa.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | 02/02/2015 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2013 | |
Delayed Project Date | 07/01/2016 | |
Predesign Approval | ||
Design Approval | 01/01/2014 | 12/16/2013 |
Bid Auth. Approval | 03/19/2014 | 03/14/2014 |
Construction Approval | 04/30/2014 | 04/22/2014 |
Project Closeout | 01/31/2015 | 01/23/2015 |
Audit Date | 02/02/2015 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 19,124 | 0 |
Right of Way | 0 | 0 |
Total Design | 19,124 | 0 |
Construction Engineering | 19,124 | 6,906 |
Construction Contract | 127,490 | 128,730 |
Other Construction | 0 | 551 |
Total Construction | 146,614 | 136,188 |
Funding Surplus | - 36,360 | |
Total TIB Funding | 129,378 | 136,188 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GRANITE FALLS | 6,810 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 6,810 | 5.0% |
Project Description
This project repairs areas of base failure, grinds and provides a two-inch overlay of Mountain Loop Highway bewteen Alpine Drive and 300 feet south of Quarry Road.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |