City of Gold Bar's 2024 Seal Coat

2-P-819(008)-1

2-P-819(008)-1
2024 Seal Coat

Multiple Locations

FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $91,941

County: Snohomish   |   Legislative District: 12   |   Project Length: 0.43   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 10/31/2024

Project Information

Lead Agency GOLD BAR
Funding Year 2025
Program SCPP
Current Phase Audit
Legislative District 12
Congressional District 8
Federal Route Number 9999
Project Length 0.43 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Rich Norris
Contact Email r.norris@cityofgoldbar.us
TIB Engineer Greg Armstrong
Last Payment Date 10/31/2024

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
Predesign Approval
Design Approval 12/31/2023 12/06/2023
Bid Auth. Approval 04/30/2024 04/29/2024
Construction Approval 05/16/2024 05/23/2024
Project Closeout 10/15/2024 10/17/2024
Audit Date   10/31/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 22,640 26,667
Right of Way 0 0
Total Design 22,640 26,667
     
Construction Engineering 11,330 7,960
Construction Contract 124,530 62,105
Other Construction 0 0
Total Construction 135,860 70,065
     
Funding Surplus - 66,559  
Total TIB Funding 91,941 96,732

Local Funding Partners

Funding Amount Percent
GOLD BAR 4,791 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 4,791 5.0%

Project Description

Chip seal the following segments Prospector Lane - Smeltzer Rd to W EOR Smeltzer Road - 1st Ave W to Verlinde Ave Verlinda Avenue - Smeltzer Rd to W C/L

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.