Existing sidewalk in badly deteriorated condition.
Projects — TIB Project Information
TIB Project Information
Town of Wilkeson's Church Street Sidewalk
2-P-816(001)-1
2-P-816(001)-1
Church Street Sidewalk
Post Office to Forest Service
FY 2008 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $40,654
County: Pierce | Legislative District: 31 | Project Length: 0.03 | TIB Engineer: Greg Armstrong | Last Payment Date: 12/19/2007
Project Information
Lead Agency | WILKESON |
Funding Year | 2008 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 31 |
Congressional District | 8 |
Federal Route Number | 0165 |
Project Length | 0.03 mi. |
ADT | 500 |
Functional Class | Collector |
Type of Work | Pedestrian |
Project Contact | Janet Kepka |
Contact Email | wilkeson@linxure.net |
TIB Engineer | Greg Armstrong |
Last Payment Date | 12/19/2007 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 05/18/2007 | |
Delayed Project Date | 07/01/2009 | |
Predesign Approval | ||
Design Approval | 05/18/2007 | 05/18/2007 |
Bid Auth. Approval | 05/18/2007 | 05/18/2007 |
Construction Approval | 12/30/2007 | 09/12/2007 |
Project Closeout | 12/30/2007 | 12/19/2007 |
Audit Date | 12/19/2007 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 1,000 |
Right of Way | 0 | 0 |
Total Design | 0 | 1,000 |
Construction Engineering | 0 | 3,000 |
Construction Contract | 30,000 | 36,654 |
Other Construction | 0 | 0 |
Total Construction | 30,000 | 39,654 |
Funding Increase | 10,654 | |
Total TIB Funding | 40,654 | 40,654 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WILKESON | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Construct 180 feet of 13-foot wide sidewalk.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |