TIB Project Information

Town of Eatonville's 2025 Chip Seal

2-P-811(007)-1

2-P-811(007)-1
2025 Chip Seal

Multiple Locations

FY 2026 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $159,652

County: Pierce   |   Legislative District: 2   |   Project Length: 0.56   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 03/20/2025

Project Information

Lead Agency EATONVILLE
Funding Year 2026
Program SCPP
Current Phase Design
Legislative District 2
Congressional District 8
Federal Route Number 9999
Project Length 0.56 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Eric Phillips
Contact Email townadmin@eatonville-wa.gov
TIB Engineer Greg Armstrong
Last Payment Date 03/20/2025

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
Predesign Approval
Design Approval 01/14/2025 01/16/2025
Bid Auth. Approval 11/05/2025
Construction Approval 01/20/2026
Project Closeout 09/04/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 20,897 22,000
Right of Way 0 0
Total Design 20,897 22,000
     
Construction Engineering 12,633 13,300
Construction Contract 126,122 132,780
Other Construction 0 0
Total Construction 138,755 146,080
     
Total TIB Funding 159,652 168,080

Local Funding Partners

Funding Amount Percent
EATONVILLE 8,428 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 8,428 5.0%

Project Description

Chip seal the foloowing segments Center Street W - Antonie Ave N to View Crest Dr Center Street W - View Crest Dr to Gracie Ln W Cedar Avenue N - Eatonville Hwy W to Carter St W

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments