The pavement condition rating of this segment of Carbonado-Wilkeson Road is 48.
Projects — TIB Project Information
TIB Project Information
Town of Carbonado's FY 2022 Overlay Project
2-P-809(003)-1
2-P-809(003)-1
FY 2022 Overlay Project
Multiple Locations
FY 2022 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $190,182
County: Pierce | Legislative District: 31 | Project Length: 0.19 | TIB Engineer: Greg Armstrong | Last Payment Date: 01/17/2023
Project Information
Lead Agency | CARBONADO |
Funding Year | 2022 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 31 |
Congressional District | 8 |
Federal Route Number | 9999 |
Project Length | 0.19 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Daillene Argo |
Contact Email | clerk@carbonado.org |
TIB Engineer | Greg Armstrong |
Last Payment Date | 01/17/2023 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2020 | |
Delayed Project Date | 07/01/2023 | |
Predesign Approval | ||
Design Approval | 12/15/2020 | 12/16/2020 |
Bid Auth. Approval | 03/15/2022 | 03/15/2022 |
Construction Approval | 05/12/2022 | 05/10/2022 |
Project Closeout | 01/10/2023 | 01/04/2023 |
Audit Date | 01/17/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 10,450 | 0 |
Right of Way | 0 | 0 |
Total Design | 10,450 | 0 |
Construction Engineering | 10,450 | 2,960 |
Construction Contract | 112,556 | 197,231 |
Other Construction | 0 | 0 |
Total Construction | 123,006 | 200,191 |
Funding Increase | 56,726 | |
Total TIB Funding | 190,182 | 200,191 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CARBONADO | 10,009 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 10,009 | 5.0% |
Project Description
This project repairs area of pavement failure and provides a 2-inch overlay of Carbonado-Wilkeson Road between AP Tubbs Road and City limits
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |