Projects — TIB Project Information
TIB Project Information
City of Buckley's FY 2009 Overlay Project
2-P-808(002)-1
2-P-808(002)-1
FY 2009 Overlay Project
Multiple Locations
FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $100,000
County: Pierce | Legislative District: 31 | Project Length: 0.25 | TIB Engineer: Greg Armstrong | Last Payment Date: 09/08/2008
Project Information
Lead Agency | BUCKLEY |
Funding Year | 2009 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 31 |
Congressional District | 8 |
Federal Route Number | 9999 |
Project Length | 0.25 mi. |
ADT | 500 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Dave Schmidt |
Contact Email | dschmidt@cityofbuckley.com |
TIB Engineer | Greg Armstrong |
Last Payment Date | 09/08/2008 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2007 | |
Delayed Project Date | 07/01/2010 | |
Predesign Approval | ||
Design Approval | 01/01/2008 | 12/06/2007 |
Bid Auth. Approval | 01/01/2008 | 12/06/2007 |
Construction Approval | 03/20/2008 | 03/13/2008 |
Project Closeout | 09/01/2008 | 09/05/2008 |
Audit Date | 09/08/2008 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 6,915 |
Right of Way | 0 | 0 |
Total Design | 0 | 6,915 |
Construction Engineering | 0 | 0 |
Construction Contract | 71,792 | 116,286 |
Other Construction | 0 | 0 |
Total Construction | 71,792 | 116,286 |
Funding Increase | 28,208 | |
Total TIB Funding | 100,000 | 123,201 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
BUCKLEY | 23,201 | 18.8% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 23,201 | 27.3% |
Project Description
This project consists of the grind and 2 inch overlay of West Main Street between SR-410 and Naches Street.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |