TIB Project Information

City of North Bend's Overlay Project

2-P-804(001)-1

2-P-804(001)-1
Overlay Project

City of North Bend

FY 2007 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $64,014

County: King   |   Legislative District: 5   |   Project Length: 1,017.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 01/02/2007

Project Information

Lead Agency NORTH BEND
Funding Year 2007
Program SCPP
Current Phase Audit
Legislative District 5
Congressional District 8
Federal Route Number 9999
Project Length 1017.00 mi.
ADT 300
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Ron Garrow
Contact Email rong@ci.north-bend.wa.us
TIB Engineer Greg Armstrong
Last Payment Date 01/02/2007

Project Schedule

  Target Date Actual Date
Project Selection Date   01/27/2006
Delayed Project Date 07/01/2008  
Predesign Approval
Design Approval 01/27/2006
Bid Auth. Approval 01/27/2006 01/27/2006
Construction Approval 09/30/2006 09/01/2006
Project Closeout 01/15/2007 01/02/2007
Audit Date   01/02/2007
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 794
Right of Way 0 0
Total Design 0 794
     
Construction Engineering 0 5,996
Construction Contract 103,014 28,386
Other Construction 0 28,838
Total Construction 103,014 63,220
     
Funding Surplus - 39,000  
Total TIB Funding 64,014 64,014

Local Funding Partners

Funding Amount Percent
NORTH BEND 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Small City Preservation Overlay Project

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments