Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Black Diamond's FY 2022 Overlay Project

2-P-800(010)-1

2-P-800(010)-1
FY 2022 Overlay Project

Multiple Locations

FY 2022 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $99,842

County: King   |   Legislative District: 5   |   Project Length: 0.41   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 11/01/2021

Project Information

Lead Agency BLACK DIAMOND
Funding Year 2022
Program SCPP
Current Phase Audit
Legislative District 5
Congressional District 8
Federal Route Number 9999
Project Length 0.41 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Scott Hanis
Contact Email shanis@blackdiamondwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 11/01/2021

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2020
Delayed Project Date 07/01/2023  
Predesign Approval
Design Approval 12/18/2020 12/18/2020
Bid Auth. Approval 04/10/2021 04/12/2021
Construction Approval 04/30/2021 04/27/2021
Project Closeout 10/31/2021 10/25/2021
Audit Date   11/01/2021
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 3,783 3,353
Right of Way 0 0
Total Design 3,783 3,353
     
Construction Engineering 1,955 2,142
Construction Contract 123,811 117,839
Other Construction 0 2,171
Total Construction 125,766 122,152
     
Funding Increase 7,608  
Funding Surplus - 37,315  
Total TIB Funding 99,842 125,505

Local Funding Partners

Funding Amount Percent
BLACK DIAMOND 25,663 20.4%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 25,663 20.4%

Project Description

This project repairs areas of pavement failure, provides a 2-inch overlay and upgrades 3 ADA ramps on the following segments 6th Avenue - Lawson Street to Baker Street Hammond Street - 5th Avenue to 6th Avenue Hammond Place - Baker Street to end of road Park Street - 3rd Avenue to 4th Avenue 4th Avenue - Park Street to James Street James Street - 3rd Street to 4th Street

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.