City of Black Diamond's FY 2021 Overlay Project
2-P-800(008)-1
2-P-800(008)-1
FY 2021 Overlay Project
Multiple Locations
FY 2021 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $79,633
County: King | Legislative District: 5 | Project Length: 0.62 | TIB Engineer: Greg Armstrong | Last Payment Date: 07/15/2020
Project Information
Lead Agency | BLACK DIAMOND |
Funding Year | 2021 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 5 |
Congressional District | 8 |
Federal Route Number | 9999 |
Project Length | 0.62 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Scott Hanis |
Contact Email | shanis@blackdiamondwa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 07/15/2020 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2019 | |
Delayed Project Date | 07/01/2022 | |
Predesign Approval | ||
Design Approval | 02/01/2020 | 12/30/2019 |
Bid Auth. Approval | 03/15/2020 | 03/17/2020 |
Construction Approval | 04/13/2020 | 04/20/2020 |
Project Closeout | 10/31/2020 | 07/07/2020 |
Audit Date | 07/15/2020 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 2,550 | 3,225 |
Right of Way | 0 | 0 |
Total Design | 2,550 | 3,225 |
Construction Engineering | 3,825 | 1,914 |
Construction Contract | 133,726 | 86,251 |
Other Construction | 0 | 2,296 |
Total Construction | 137,551 | 90,461 |
Funding Surplus | - 60,468 | |
Total TIB Funding | 79,633 | 93,686 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
BLACK DIAMOND | 14,053 | 15.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 14,053 | 15.0% |
Project Description
Grind, 2-inch overlay and pavement repair of the following segments 232nd Avenue SE - SE 288th St to SE 293rd St SE 312th Street - 224th Avenue SE to End of Road
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |