City of Black Diamond's FY 2018 Overlay Project
2-P-800(005)-1
2-P-800(005)-1
FY 2018 Overlay Project
Multiple Locations
FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $28,547
County: King | Legislative District: 5 | Project Length: 0.10 | TIB Engineer: Greg Armstrong | Last Payment Date: 12/27/2017
Project Information
Lead Agency | BLACK DIAMOND |
Funding Year | 2018 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 5 |
Congressional District | 8 |
Federal Route Number | 1306 |
Project Length | 0.10 mi. |
ADT | 500 |
Functional Class | Minor |
Type of Work | Resurfacing |
Project Contact | Scott Hanis |
Contact Email | shanis@ci.blackdiamond.wa.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | 12/27/2017 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2016 | |
Delayed Project Date | 07/01/2019 | |
Predesign Approval | ||
Design Approval | 02/28/2017 | 03/01/2017 |
Bid Auth. Approval | 06/06/2017 | 06/08/2017 |
Construction Approval | 06/27/2017 | 06/30/2017 |
Project Closeout | 12/31/2017 | 12/20/2017 |
Audit Date | 12/27/2017 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 5,950 | 8,338 |
Right of Way | 0 | 0 |
Total Design | 5,950 | 8,338 |
Construction Engineering | 1,700 | 926 |
Construction Contract | 55,586 | 29,642 |
Other Construction | 0 | 0 |
Total Construction | 57,286 | 30,568 |
Funding Surplus | - 34,689 | |
Total TIB Funding | 28,547 | 38,906 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
BLACK DIAMOND | 10,359 | 26.6% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 10,359 | 26.6% |
Project Description
This project repairs areas of pavement failure, grinds and provides a 2-inch overlay of the eastbound lane of Roberts Drive between 236th Ave SE and 100 feet west of the Rock Creek Bridge (westbound lane will be overlaid by the developer)
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |