City of Black Diamond's FY 2017 Overlay Project
2-P-800(004)-1
2-P-800(004)-1
FY 2017 Overlay Project
Multiple Locations
FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $98,585
County: King | Legislative District: 5 | Project Length: 0.25 | TIB Engineer: Greg Armstrong | Last Payment Date: 09/16/2016
Project Information
Lead Agency | BLACK DIAMOND |
Funding Year | 2017 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 5 |
Congressional District | 8 |
Federal Route Number | 9999 |
Project Length | 0.25 mi. |
ADT | 100 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Scott Hanis |
Contact Email | shanis@ci.blackdiamond.wa.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | 09/16/2016 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2015 | |
Delayed Project Date | 07/01/2018 | |
Predesign Approval | ||
Design Approval | 01/15/2016 | 12/28/2015 |
Bid Auth. Approval | 04/15/2016 | 04/12/2016 |
Construction Approval | 05/10/2016 | 05/02/2016 |
Project Closeout | 09/23/2016 | 09/06/2016 |
Audit Date | 09/16/2016 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 24,562 | 11,941 |
Right of Way | 0 | 0 |
Total Design | 24,562 | 11,941 |
Construction Engineering | 4,050 | 2,625 |
Construction Contract | 102,107 | 96,328 |
Other Construction | 4,500 | 0 |
Total Construction | 110,657 | 98,953 |
Funding Increase | 15,772 | |
Funding Surplus | - 52,406 | |
Total TIB Funding | 98,585 | 110,894 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
BLACK DIAMOND | 12,309 | 11.1% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 12,309 | 11.1% |
Project Description
This project repairs areas of base failure, grinds and provides a 2-inch overlay of Jones Lake Road from SR 169 to Railroad Avenue.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |