City of Black Diamond's FY 2009 Overlay Project
2-P-800(001)-1
2-P-800(001)-1
FY 2009 Overlay Project
Multiple Locations
FY 2009 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $94,856
County: King | Legislative District: 5 | Project Length: 0.51 | TIB Engineer: Greg Armstrong | Last Payment Date: 10/06/2008
Project Information
Lead Agency | BLACK DIAMOND |
Funding Year | 2009 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 5, 47 |
Congressional District | 8 |
Federal Route Number | 1383 |
Project Length | 0.51 mi. |
ADT | 6,000 |
Functional Class | Minor |
Type of Work | Resurfacing |
Project Contact | Seth Boettcher |
Contact Email | sboettcher@ci.blackdiamond.wa.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | 10/06/2008 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2007 | |
Delayed Project Date | 07/01/2010 | |
Predesign Approval | ||
Design Approval | 03/01/2008 | 02/25/2008 |
Bid Auth. Approval | 03/01/2008 | 02/25/2008 |
Construction Approval | 08/21/2008 | 08/08/2008 |
Project Closeout | 10/31/2008 | 10/08/2008 |
Audit Date | 10/06/2008 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 102,460 | 94,856 |
Other Construction | 0 | 0 |
Total Construction | 102,460 | 94,856 |
Funding Increase | 1,882 | |
Funding Surplus | - 9,486 | |
Total TIB Funding | 94,856 | 94,856 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
BLACK DIAMOND | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project consists of a 2 inch overlay and 1,850 square feet of dig outs on Lake Sawyer Road SE between Auburn-Black Diamond Road and 0.5 miles north (City Limits)
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |