TIB Project Information
Town of Ruston's FY 2021 Seal Coat Project
2-P-135(002)-1
2-P-135(002)-1
FY 2021 Seal Coat Project
Multiple Locations
FY 2021 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $73,722
County: Pierce | Legislative District: 27 | Project Length: 0.46 | TIB Engineer: Greg Armstrong | Last Payment Date: 03/15/2022
Project Information
Lead Agency | RUSTON |
Funding Year | 2021 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 27 |
Congressional District | 6 |
Federal Route Number | 9999 |
Project Length | 0.46 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Rob White |
Contact Email | robw@rustonwa.org |
TIB Engineer | Greg Armstrong |
Last Payment Date | 03/15/2022 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2019 | |
Delayed Project Date | 07/01/2022 | |
Predesign Approval | ||
Design Approval | 02/01/2020 | 01/13/2020 |
Bid Auth. Approval | 04/01/2020 | 01/13/2020 |
Construction Approval | 05/01/2020 | 01/13/2020 |
Project Closeout | 03/01/2022 | 03/17/2022 |
Audit Date | 03/15/2022 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 44,516 | 3,845 |
Construction Contract | 142,573 | 74,487 |
Other Construction | 0 | 0 |
Total Construction | 187,089 | 78,332 |
Funding Surplus | - 113,367 | |
Total TIB Funding | 73,722 | 78,332 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
RUSTON | 4,610 | 5.9% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 4,610 | 5.9% |
Project Description
Chip seal the following segments 50th Street - North Pearl Street to North Winnifred Street Shirley Street - City Limits to N 49th Street Bennett Street - City Limits to N Court Street Rust Way - Winnifred Street to Baltimore Street
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |