Projects — TIB Project Information
TIB Project Information
Town of Yarrow Point's FY 2014 Overlay Project
2-P-120(001)-1
2-P-120(001)-1
FY 2014 Overlay Project
Multiple Locations
FY 2014 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $100,000
County: King | Legislative District: 48 | Project Length: 0.56 | TIB Engineer: Greg Armstrong | Last Payment Date: 04/21/2015
Project Information
Lead Agency | YARROW POINT |
Funding Year | 2014 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 48 |
Congressional District | 1 |
Federal Route Number | 2011 |
Project Length | 0.56 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Stacia Schroeder |
Contact Email | sschroeder@ci.yarrow-point.wa.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | 04/21/2015 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2012 | |
Delayed Project Date | 07/01/2015 | |
Predesign Approval | ||
Design Approval | 01/01/2013 | 12/12/2012 |
Bid Auth. Approval | 06/01/2013 | 12/12/2012 |
Construction Approval | 07/01/2013 | 12/12/2012 |
Project Closeout | 04/30/2015 | 04/15/2015 |
Audit Date | 04/21/2015 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 100,000 | 205,000 |
Other Construction | 0 | 0 |
Total Construction | 100,000 | 205,000 |
Total TIB Funding | 100,000 | 205,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
YARROW POINT | 105,000 | 51.2% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 105,000 | 51.2% |
Project Description
This project will grind, prelevel and provide a 2-inch overlay of 92nd Avenue NE between NE 34th St and NE 42nd St.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |