TIB Project Information

City of Algona's 2021 Overlay

2-P-119(005)-1

2-P-119(005)-1
2021 Overlay

Multiple Locations

FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $189,437

County: King   |   Legislative District: 30   |   Project Length: 0.52   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 11/01/2022

Project Information

Lead Agency ALGONA
Funding Year 2023
Program SCPP
Current Phase Audit
Legislative District 30
Congressional District 8
Federal Route Number 9999
Project Length 0.52 mi.
ADT 150
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Salvador Marez
Contact Email salvadorm@algonawa.gov
TIB Engineer Greg Armstrong
Last Payment Date 11/01/2022

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 07/01/2024  
Predesign Approval
Design Approval 02/01/2022 12/06/2021
Bid Auth. Approval 05/12/2022 05/12/2022
Construction Approval 06/06/2022 06/16/2022
Project Closeout 10/31/2022 10/31/2022
Audit Date   11/01/2022
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 27,000 30,000
Right of Way 0 0
Total Design 27,000 30,000
     
Construction Engineering 27,000 30,000
Construction Contract 180,000 161,912
Other Construction 0 0
Total Construction 207,000 191,912
     
Funding Surplus - 44,563  
Total TIB Funding 189,437 221,912

Local Funding Partners

Funding Amount Percent
ALGONA 32,475 14.6%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 32,475 14.6%

Project Description

Grinds and provide a 2-inch overlay of the follow segments 5th Ave N - Algona Blvd N to Chicago Ave - 2 ADA Ramps 4th Ave S - Tacoma Blvd to Washington Blvd

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments