City of Algona's FY 2020 Rehabilitation Project

2-P-119(003)-1

2-P-119(003)-1
FY 2020 Rehabilitation Project

Multiple Locations

FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $308,907

County: King   |   Legislative District: 30   |   Project Length: 0.52   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 09/03/2019

Project Information

Lead Agency ALGONA
Funding Year 2020
Program SCPP
Current Phase Audit
Legislative District 30
Congressional District 8
Federal Route Number 9999
Project Length 0.52 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact James Griess
Contact Email jimmyg@algonawa.gov
TIB Engineer Greg Armstrong
Last Payment Date 09/03/2019

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2018
Delayed Project Date 07/01/2021  
Predesign Approval
Design Approval 01/01/2019 12/11/2018
Bid Auth. Approval 04/04/2019 04/05/2019
Construction Approval 04/30/2019 05/01/2019
Project Closeout 10/31/2019 08/26/2019
Audit Date   09/03/2019
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 24,947 29,000
Right of Way 0 0
Total Design 24,947 29,000
     
Construction Engineering 24,947 29,000
Construction Contract 243,896 308,598
Other Construction 0 0
Total Construction 268,843 337,598
     
Funding Increase 31,528  
Funding Surplus - 16,411  
Total TIB Funding 308,907 366,598

Local Funding Partners

Funding Amount Percent
ALGONA 57,691 15.7%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 57,691 15.7%

Project Description

This project rehabiliates the following segments using full depth reclamation and 2-inches of HMA 3rd Avenue S - Seatlle Blvd S to Milwaukee Blvd S Washington Boulevard - 2nd Avenue to 5th Avenue S

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.