City of Clyde Hill's 2024 Overlay

2-P-115(004)-1

2-P-115(004)-1
2024 Overlay

Multiple Locations

FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $129,361

County: King   |   Legislative District: 48   |   Project Length: 0.20   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 08/29/2024

Project Information

Lead Agency CLYDE HILL
Funding Year 2025
Program SCPP
Current Phase Audit
Legislative District 48
Congressional District 1
Federal Route Number 9999
Project Length 0.20 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Shaun Tozer
Contact Email shaun@clydehill.org
TIB Engineer Greg Armstrong
Last Payment Date 08/29/2024

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
Predesign Approval
Design Approval 01/03/2024 12/19/2023
Bid Auth. Approval 03/20/2024 03/06/2024
Construction Approval 03/27/2024 04/01/2024
Project Closeout 09/30/2024 08/19/2024
Audit Date   08/29/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 25,568 0
Right of Way 0 0
Total Design 25,568 0
     
Construction Engineering 0 25,154
Construction Contract 124,432 150,230
Other Construction 0 0
Total Construction 124,432 175,384
     
Funding Surplus - 20,639  
Total TIB Funding 129,361 175,384

Local Funding Partners

Funding Amount Percent
CLYDE HILL 46,023 26.2%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 46,023 26.2%

Project Description

Grind and 2-inch overlay of the following segments NE 19th Place - 86th Ave to W EOR NE 19th Place - 86th Ave to E EOR NE 15th Place - 88th Ave to E EOR

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.