City of Clyde Hill's Citywide Crack Seal
2-P-115(003)-1
2-P-115(003)-1
Citywide Crack Seal
Various
FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $46,198
County: King | Legislative District: 48 | Project Length: 4.17 | TIB Engineer: Greg Armstrong | Last Payment Date: 10/17/2022
Project Information
Lead Agency | CLYDE HILL |
Funding Year | 2023 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 48 |
Congressional District | 1 |
Federal Route Number | 9999 |
Project Length | 4.17 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Shaun Tozer |
Contact Email | Shaun@Clydehill.org |
TIB Engineer | Greg Armstrong |
Last Payment Date | 10/17/2022 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 08/03/2022 | |
Delayed Project Date | 07/01/2025 | |
Predesign Approval | ||
Design Approval | 08/10/2022 | 08/10/2022 |
Bid Auth. Approval | 08/10/2022 | 08/10/2022 |
Construction Approval | 08/10/2022 | 08/10/2022 |
Project Closeout | 10/31/2022 | 10/05/2022 |
Audit Date | 10/17/2022 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 34,650 | 51,331 |
Other Construction | 0 | 0 |
Total Construction | 34,650 | 51,331 |
Funding Increase | 11,548 | |
Total TIB Funding | 46,198 | 51,331 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CLYDE HILL | 5,133 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 5,133 | 10.0% |
Project Description
22,000 linear feet of crack seal
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |