City of Clyde Hill's FY 2020 Overlay Project

2-P-115(002)-1

2-P-115(002)-1
FY 2020 Overlay Project

Multiple Locations

FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $232,021

County: King   |   Legislative District: 48   |   Project Length: 0.66   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 08/01/2019

Project Information

Lead Agency CLYDE HILL
Funding Year 2020
Program SCPP
Current Phase Audit
Legislative District 48
Congressional District 1
Federal Route Number 2058
Project Length 0.66 mi.
ADT 0
Functional Class Collector
Type of Work Resurfacing
Project Contact Arnie Clark
Contact Email Arnie@clydehill.org
TIB Engineer Greg Armstrong
Last Payment Date 08/01/2019

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2018
Delayed Project Date 07/01/2021  
Predesign Approval
Design Approval 01/01/2019 01/02/2019
Bid Auth. Approval 01/01/2019 01/02/2019
Construction Approval 01/23/2019 01/24/2019
Project Closeout 12/31/2019 07/12/2019
Audit Date   08/01/2019
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 15,864 47,759
Right of Way 0 0
Total Design 15,864 47,759
     
Construction Engineering 2,497 16,732
Construction Contract 231,639 498,083
Other Construction 0 0
Total Construction 234,136 514,815
     
Funding Increase 37,260  
Funding Surplus - 55,239  
Total TIB Funding 232,021 562,574

Local Funding Partners

Funding Amount Percent
CLYDE HILL 330,553 58.8%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 330,553 58.8%

Project Description

This project grinds and provides a 2-inch overlay of the following segments NE 24th Street between 84th Ave NE and 92nd Ave NE NE 24th Street between 94th Ave NE and 185ft e/o 95th 85th Place NE between NE 24th Street and Cul-De-Sac 88th Avenue NE between NE 24th St to 220' north allong 88th Ave NE 88th Place NE between NE 24th St and Cul-De-Sac

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments