City of Medina's 2024 Overlay
2-P-109(007)-1
2-P-109(007)-1
2024 Overlay
Multiple Locations
FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $104,788
County: King | Legislative District: 48 | Project Length: 0.08 | TIB Engineer: Greg Armstrong | Last Payment Date: 10/31/2024
Project Information
Lead Agency | MEDINA |
Funding Year | 2025 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 48 |
Congressional District | 1 |
Federal Route Number | 9999 |
Project Length | 0.08 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Ryan Osada |
Contact Email | rosada@medina-wa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 10/31/2024 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
Predesign Approval | ||
Design Approval | 02/01/2024 | 12/06/2023 |
Bid Auth. Approval | 04/01/2024 | 03/29/2024 |
Construction Approval | 04/23/2024 | 04/24/2024 |
Project Closeout | 12/31/2024 | 10/17/2024 |
Audit Date | 10/31/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 13,437 | 14,314 |
Right of Way | 0 | 0 |
Total Design | 13,437 | 14,314 |
Construction Engineering | 13,437 | 650 |
Construction Contract | 111,870 | 105,944 |
Other Construction | 0 | 0 |
Total Construction | 125,307 | 106,594 |
Funding Increase | 9,984 | |
Funding Surplus | - 43,940 | |
Total TIB Funding | 104,788 | 120,908 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MEDINA | 16,120 | 13.3% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 16,120 | 13.3% |
Project Description
Grind and 2-inch overlay with spot pavement repairs of the following segments NE 26th Street - 82nd Ave NE to E EOR 88th Avenue NE - NE 10th St to S EOR
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |