TIB Project Information

City of Medina's City-wide Crack Seal

2-P-109(004)-1

2-P-109(004)-1
City-wide Crack Seal

FY 2022 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $36,405

County: King   |   Legislative District: 48   |   Project Length: 5.15   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 09/16/2022

Project Information

Lead Agency MEDINA
Funding Year 2022
Program SCPP
Current Phase Audit
Legislative District 48
Congressional District 1
Federal Route Number 9999
Project Length 5.15 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Ryan Osada
Contact Email rosada@medina-wa.gov
TIB Engineer Greg Armstrong
Last Payment Date 09/16/2022

Project Schedule

  Target Date Actual Date
Project Selection Date   06/15/2022
Delayed Project Date 07/01/2024  
Predesign Approval
Design Approval 06/25/2022 06/16/2022
Bid Auth. Approval 06/25/2022 06/16/2022
Construction Approval 06/25/2022 06/16/2022
Project Closeout 09/30/2022 09/12/2022
Audit Date   09/16/2022
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 36,405 44,100
Other Construction 0 0
Total Construction 36,405 44,100
     
Total TIB Funding 36,405 44,100

Local Funding Partners

Funding Amount Percent
MEDINA 7,695 17.4%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 7,695 17.4%

Project Description

30000 linear feet of Crack Seal

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments