City of Medina's FY 2017 Overlay Project

2-P-109(001)-1

2-P-109(001)-1
FY 2017 Overlay Project

Multiple Locations

FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $101,565

County: King   |   Legislative District: 48   |   Project Length: 0.27   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 08/30/2017

Project Information

Lead Agency MEDINA
Funding Year 2017
Program SCPP
Current Phase Audit
Legislative District 48
Congressional District 1
Federal Route Number 9999
Project Length 0.27 mi.
ADT 150
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Ryan Osada
Contact Email rosada@medina-wa.gov
TIB Engineer Greg Armstrong
Last Payment Date 08/30/2017

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2015
Delayed Project Date 07/01/2018  
Predesign Approval
Design Approval 01/15/2016 12/21/2015
Bid Auth. Approval 08/05/2016 08/03/2016
Construction Approval 08/22/2016 08/22/2016
Project Closeout 08/31/2017 08/14/2017
Audit Date   08/30/2017
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 16,000 12,073
Right of Way 0 0
Total Design 16,000 12,073
     
Construction Engineering 6,000 16,071
Construction Contract 96,300 99,236
Other Construction 1,600 0
Total Construction 103,900 115,307
     
Funding Surplus - 18,335  
Total TIB Funding 101,565 127,380

Local Funding Partners

Funding Amount Percent
MEDINA 25,815 20.3%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 25,815 20.3%

Project Description

This project repairs areas of base failure, grinds and provides a 2-inch overlay of NE 32nd Street from Evergreen Point Road to 78th Place NE.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments