City of Omak's 2022 Chip Seal Award
2-E-987(007)-1
2-E-987(007)-1
2022 Chip Seal Award
Multiple Locations
FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $142,581
County: Okanogan | Legislative District: 7 | Project Length: 2.20 | TIB Engineer: Andrew Beagle | Last Payment Date: 10/01/2024
Project Information
Lead Agency | OMAK |
Funding Year | 2024 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 7 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 2.20 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Wayne Beetchenow |
Contact Email | publicworks@omakcity.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 10/01/2024 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 01/01/2024 | |
Predesign Approval | ||
Design Approval | 02/01/2023 | 03/13/2023 |
Bid Auth. Approval | 03/01/2024 | 05/22/2024 |
Construction Approval | 05/01/2024 | 05/22/2024 |
Project Closeout | 12/01/2024 | 09/18/2024 |
Audit Date | 10/01/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 87,495 | 112,257 |
Other Construction | 0 | 37,963 |
Total Construction | 87,495 | 150,220 |
Funding Increase | 55,086 | |
Total TIB Funding | 142,581 | 150,220 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
OMAK | 7,639 | 5.1% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 7,639 | 5.1% |
Project Description
Chip Seal of the following segments Jackson Street - SR 155 to 8th Ave E 8th Avenue E - Jackson St to Dayton St Edmonds Street S - 5th Avenue E to 8th Avenue E Ferry Street - N EOR to 8th Avenue E 5th Avenue E - Edmonds St S to Hanford St S 6th Avenue E - Dayton St to E C/L 7th Avenue E - Dayton St to E C/L Index Street S - 6th Ave E to 8th Ave E Hanford Street - SR 155 to 8th Ave E Garfield Street - SR 155 to 8th Ave E Dayton Street - 6th Ave E to 8th Ave E
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |