The pavement condition ratings for the segment are as follow Koala Drive - Quince to C/L 54 Shumway Road - Koala Dr to C/L 54 Quince Street - SR 215 to Koala Dr 68 Omache Drive - SR 215 to Koala Dr 54 Oak Street - Dewberry Ave to C/L 70 Locust Street - S of Dewberry Ave to C/L 76 E Dewberry Avenue - SR 97 to Juniper St 76 W Cherry Avenue - SR 215 to C/L 65 E Cherry Avenue - SR 215 to end 65 Juniper Street - S End to SR 215 60 W Dewberry Avenue - W End to SR 215 64 Elberta Avenue - W End to Ironwood 70
Projects — TIB Project Information
TIB Project Information
City of Omak's 2021 Seal Coat
2-E-987(006)-1
2-E-987(006)-1
2021 Seal Coat
Multiple Locations
FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $157,837
County: Okanogan | Legislative District: 7 | Project Length: 4.65 | TIB Engineer: Andrew Beagle | Last Payment Date: 01/31/2023
Project Information
Lead Agency | OMAK |
Funding Year | 2023 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 7 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 4.65 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Ken Mears |
Contact Email | publicworks@omakcity.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 01/31/2023 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
Predesign Approval | ||
Design Approval | 02/01/2022 | 03/16/2022 |
Bid Auth. Approval | 04/10/2022 | 05/03/2022 |
Construction Approval | 05/01/2022 | 05/03/2022 |
Project Closeout | 09/01/2022 | 01/24/2023 |
Audit Date | 01/31/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 167,483 | 166,144 |
Other Construction | 0 | 0 |
Total Construction | 167,483 | 166,144 |
Funding Surplus | - 9,646 | |
Total TIB Funding | 157,837 | 166,144 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
OMAK | 8,307 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 8,307 | 5.0% |
Project Description
Chip seal.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |