The streets in the southeast area of Omak are aged BST with localized deterioration. The current pavement condition ratings are 3rd Ave - Asotin to SR 15563 2nd Ave - Benton to Columbia72 Asotin St - Railroad to 3rd68 Benton St - 5th to SR 15563 Railroad - Asotin to Dayton68 5th Ave - Benton to E End72 Columbia St - 5th to SR 15563 Edmonds St - S End to SR 15563 4th Ave - Dayton to Ferry72 Ferry St - 4th to SR 15563
Projects — TIB Project Information
TIB Project Information
City of Omak's FY 2020 Seal Coat Project
2-E-987(004)-1
2-E-987(004)-1
FY 2020 Seal Coat Project
Multiple Locations
FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $45,790
County: Okanogan | Legislative District: 7 | Project Length: 1.89 | TIB Engineer: Andrew Beagle | Last Payment Date: 12/16/2019
Project Information
Lead Agency | OMAK |
Funding Year | 2020 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 7 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 1.89 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Ken Mears |
Contact Email | publicworks@omakcity.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 12/16/2019 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2018 | |
Delayed Project Date | 07/01/2021 | |
Predesign Approval | ||
Design Approval | 01/01/2019 | 01/16/2019 |
Bid Auth. Approval | 03/01/2019 | 01/16/2019 |
Construction Approval | 04/01/2019 | 01/16/2019 |
Project Closeout | 12/31/2019 | 12/04/2019 |
Audit Date | 12/16/2019 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 62,598 | 48,200 |
Other Construction | 0 | 130 |
Total Construction | 62,598 | 48,330 |
Funding Surplus | - 16,808 | |
Total TIB Funding | 45,790 | 48,330 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
OMAK | 2,540 | 5.3% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 2,540 | 5.3% |
Project Description
The project provides crack seal and chip seal of the approved segments. The city will complete pavement repair where needed prior to the Okanogan County chip.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |